18/8/2015

ThienNhien.Net - Phu Yen Province has signed an official letter by express check to direct blasting at quarries mining village of Phuoc Hoa, Xuan Phuoc, Dong Xuan district of JSC Investment and Construction 1.5.

ThienNhien.Net - Phu Yen Province has signed an official letter by express check to direct blasting at quarries mining village of Phuoc Hoa, Xuan Phuoc, Dong Xuan district of JSC Investment and Construction 1.5.

Mặc dù đã hết thời hạn khai thác mỏ đá nhưng Công ty Cổ phần Đầu tư và Xây dựng 1.5 vẫn hoạt động, làm nứt nhà dân, phát tán bụi ra khu dân cư.

Despite the expiry of a quarry but JSC Investment and Construction 1.5 still works, do crack houses, spread dust off neighborhoods on private cu.Thong Le Van Truc was Vice President Phu Yen People's Committee said. Accordingly, the provincial Department of Trade and Home Affairs, in collaboration with the Department of Natural Resources and Environment, Department of Construction, Dong Xuan District People's Committee and the CPC examination of specific reflection press and people in area affect; consider handle violations according to their competence, PPC previous report dated 23/7.

Earlier, people Xuan Quang Xuan Phuoc 3 and mountainous districts of Dong Xuan (Phu Yen) is pressing for JSC Investment and Construction 1.5 quarry near residential areas and cracking home environmental pollution.

Tường nhà bà Nguyễn Thị Chuyền ở thôn Phước Nhuận, xã Xuân Quang 3 bị nứt do quá trình nổ mìn và khai thác đá của Công ty Cổ phần Đầu tư và Xây dựng 1.5

Nguyen Thi Chuyen wall in the village of Phuoc Nhuan, Xuan Quang 3 cracked due to blasting and quarrying of JSC Investment and Construction 1.5

Consequently nearly 100 households were affected, of which nearly 20 households directly affected. These cracks have at least two long cracks from 0.5 meters to 2 meters on the walls and foundation, where more than 1cm wide cracks. Pressing, many people reflect on the commune, district reflects but so far has not been satisfactorily resolved.

Additionally, the quarry above the Phu Yen provincial People's Committee extended for JSC Investment and Construction 1.5 exploitation in the period from 23.03.2015 to 06.23.2015 day with a volume of 14,000 m3 . However, this time the quarry is still operating normally and the cause cracking of environmental pollution.